My current status is:
I expect my DSP in one week.
I have been paying for 4200 square feet for months zoned light industrial.
I occupy 2 suites in a 10 unit industrial complex, with neighbors on both sides.
I regestered a small still to TTB but a larger still (400l Kothe) and equipment just left Germany and will be here in 4 weeks.
I have satisfied the Department of Aggriculture (wow).
I have Oregon State approval.
Suddenly, my local building officials are concerned my building is not adequate for occupancy because I am classified as H-2 (storage of more than 30 gallons of flamable liquid). I have two hour fire walls with sprinklers but my city officials feel that this may not comply to International Fire Code.
Does anybody have any thoughts?
Thanks in advance.
Brad Irwin
soon to be... Oregon Spirit Distillers